★Cost guide
How much is low-voltage pre-wire on a new house in Kansas City? (2026)
IntegrateIT prices the low-voltage pre-wire for new construction across Overland Park and the Kansas City metro from its design center at 15108 Glenwood Ave. A new 7,000 square foot house sits in the whole-house tier: Cat6A to each television, desk, camera and access-point location, alarm rough-in, the structured-wiring panel, HDMI conduit, a fiber backbone, the Lutron HomeWorks feed, surveillance pre-wire for 8-16 cameras and audio pre-wire for 8-12 interior zones plus outdoor. Drop count, how much of the lighting, audio and security scope rides in the wire, and run length decide where inside a tier a house lands. Square footage only puts it in one. IntegrateIT is an Overland Park, Kansas integrator founded in 2021 by Daniel and Moran Alon: Control4 Platinum Dealer with a Control4 Certified Showroom, Crestron Elite Partner, Lutron Certified Dealer, CEDIA member, HTA Certified, BBB-accredited. We are a low-voltage trade partner for custom builders at 15108 Glenwood Ave in Overland Park, KS, working across Kansas City, Missouri and the Johnson County suburbs, and we price the prewire fixed against a scope-of-work document measured from the architectural plans, not estimated per square foot. Call (913) 804-7575 or email office@integrateit.tech.
Below: what each tier includes, what actually moves the number inside a tier, why the framing window is the whole ballgame, what a pre-wire deliberately excludes, and the eight questions builders and homeowners ask us most.
Pre-wire scope by home size (Kansas City, 2026)
Foundational — 4,000-6,000 sq ft
Cat6A to every television, desk, camera and access-point location; alarm rough-in; the structured-wiring panel; and HDMI conduit to the theater and media-room locations. This is the package that makes the house genuinely wired rather than nominally wired, and it is the floor we would build to on any Johnson County custom home.
Whole-house — 6,000-10,000 sq ft
Everything above, plus a fiber backbone, the low-voltage feed for Lutron HomeWorks lighting, surveillance pre-wire for 8-16 camera locations, and audio pre-wire for 8-12 interior zones plus outdoor. This is the tier a 7,000 square foot Overland Park or Leawood house lands in, and the one where the pre-wire starts carrying lighting and audio rather than only data.
Estate — 10,000+ sq ft / multi-building
Whole-house scope extended across more than one structure — main house plus pool house, guest house, barn or detached office — which means buried conduit between buildings, fiber where copper cannot reach, and a second distribution point in each outbuilding rather than one very long run.
What moves a house inside its tier
Two 7,000 square foot houses on the same street can be very different pre-wires. Square footage sets the tier; five other things decide where in it you land. Every number we give is fixed and in writing, and it comes after a no-cost site walk.
- Drop count, which is really room count and habit count. A house with six televisions, two offices, a theater and a golf simulator has roughly twice the terminations of a house of the same area with three televisions and no dedicated rooms. Terminations are labor, and labor is the number.
- How much of the lighting, audio and security scope is in the pre-wire. A data-only pre-wire and a pre-wire that also carries the Lutron HomeWorks low-voltage feed, 8-12 audio zones and 8-16 camera positions are different projects wearing the same name. This is the single largest swing inside the whole-house tier.
- Distance and structure. Long runs, tall volumes, poured-concrete lower levels, steel, and anything that has to leave the building envelope all cost more per drop. A walk-out lower level with a detached garage is not the same pull as a compact two-story footprint.
- Conduit and future-proofing. Sleeves, chases and conduit to places nobody has decided about yet are cheap now and priceless later — but they are real line items, and they are the honest reason two otherwise identical bids differ.
- How organized the build is. A pre-wire that lands once, after MEP rough-in with blocking and chases already in place, costs less than one that has to mobilize twice around unresolved conflicts. That is a schedule question, and it is worth as much as any equipment decision.
Why the framing window decides the price
The expensive part of a wire is the wall around it. Structured wiring is inexpensive at framing stage; the identical work retrofitted after drywall multiplies in labor, because every run turns into fishing, patching, texture, paint, and a negotiation about how much ceiling has to come down. On a large custom home that gap widens rather than narrows — the runs are longer, the ceilings are higher, and the finishes are far less forgiving.
The rough-in window is after framing inspection and after mechanical, electrical and plumbing rough-in, and before insulation and drywall. On-site work usually runs 5-12 days depending on the size of the house. Miss that window and you are not paying a small premium — you are paying for a different trade to undo finished work first. The full builder-side process, including the ready-for-low-voltage checklist we hand the superintendent, is on the new-construction low-voltage service page.
What the pre-wire does not include
This is where budgets go wrong, so it is worth being blunt. A pre-wire is cable, pathway, boxes, blocking, the structured-wiring panel and terminations. It is not equipment. No televisions, no speakers, no access points, no cameras, no processors, no programming, no calibration.
For scale on the equipment side: a finished home network — gateway, access points, managed PoE switching, the rack and its UPS — is its own scope, sized by square footage, how much of the house is wired and how many devices it has to carry. That is broken down in what drives the cost of a home network, and the closet those parts land in is covered on the rack build page. Lighting, audio, theater, shades and security each carry their own scope on top.
The useful way to hold the two apart: the pre-wire decides what the house is capable of, and the equipment decides what it does the week you move in. Only one of those is hard to change later.
Questions every Kansas City builder and homeowner asks
What should I budget for the low-voltage prewire on a new construction home in the Kansas City metro?
Budget against a scope-of-work document rather than against a figure, because the prewire is measured from the plans. Four things set it. Drop count: Cat6A to every television, desk, camera and access-point location, plus doors with a reader or intercom and every equipment location. How much of the lighting, audio and security scope rides in the wire — the low-voltage feed for Lutron HomeWorks, alarm rough-in, surveillance prewire, speaker back-cans and interior and outdoor audio zones each add to it. How far the runs have to travel, since a long, tall or spread-out plan costs more than a compact one of the same area. And the framing window itself: the same work retrofitted after drywall becomes fishing, patching and painting. The prewire is wire, pathway and terminations only — no equipment, no programming, which is why a prewire number and a finished-system number are different scopes. IntegrateIT prices it fixed off the drawing set after a no-cost site walk. Phone (913) 804-7575 or office@integrateit.tech.
Who does low-voltage prewire for new construction in Kansas City?
IntegrateIT — an Overland Park, Kansas integrator at 15108 Glenwood Ave, founded in 2021 by Daniel and Moran Alon, working as a low-voltage trade partner for custom builders across Kansas City, Missouri and the Johnson County suburbs. Alarm, cameras, structured wiring, AV prewire, Cat6A, fiber and the Lutron lighting feed under one trade contract: one purchase order, one certificate of insurance, one punch-list signature. Control4 Platinum Dealer with a Control4 Certified Showroom, Crestron Elite Partner, Lutron Certified Dealer, CEDIA member, HTA Certified and BBB-accredited. Every install carries a five-year workmanship warranty. Phone (913) 804-7575 or office@integrateit.tech.
We are building a 7,000 square foot house in Overland Park. What should the low-voltage pre-wire cover?
A house that size sits in the whole-house pre-wire tier: Cat6A to each television, desk, camera and access-point location, alarm rough-in, the structured-wiring panel, HDMI conduit to the theater and media room, a fiber backbone, the Lutron HomeWorks feed, surveillance pre-wire for 8-16 cameras, and audio pre-wire for 8-12 interior zones plus outdoor. Drop count, how much lighting, audio and security scope rides in the wire, and run length set the number. IntegrateIT prices it fixed off the drawing set.
What does low voltage pre-wire actually include — and what is not in it?
A pre-wire is the wire, the pathway and the terminations, installed while the walls are open. It includes the cable pulls, conduit and sleeves, back boxes and speaker back-cans, blocking for displays and access points, the structured-wiring panel and rack location, and room-by-room termination. It does not include equipment: no televisions, no speakers, no access points, no cameras, no controllers, no programming. Those are the trim-out and finish phases, quoted separately, and they are why a pre-wire number and a finished-system number are different by a large multiple.
Why is pre-wiring during framing so much cheaper than doing it later?
Because the expensive part of a wire is the wall around it. Wire is inexpensive during framing and expensive after drywall: the same work retrofitted into a finished home multiplies in labor, because every run becomes fishing, patching, painting and a conversation about how much of the ceiling has to come down. On a large custom home the gap is bigger, not smaller — the runs are longer and the finishes are less forgiving. The cheapest wire you will ever install is the one you install before the insulation.
When in the build schedule does low-voltage rough-in happen?
After framing inspection and after MEP rough-in — mechanical, electrical and plumbing — but before insulation and drywall. The on-site window is typically 5-12 days depending on the size of the home. We give the general contractor a written ready-for-low-voltage checklist before we mobilize: chases drilled, blocking placed at camera and access-point locations, MEP conflicts resolved. That is what keeps the trade from bouncing on framing punch and landing twice.
How many Cat6 drops should a new construction home have?
More than the plan says, and the reason is arithmetic rather than enthusiasm: a drop is a rounding error while the ceiling is open, and a demolition job afterward. Our default is two runs to every television location, one to every desk and permanent workstation, one to every ceiling access-point location at roughly one per 2,500 square feet, one to every camera position, one to every door with a reader or intercom, and a run to each equipment location for anything that will be permanently placed. We use Cat6A rather than Cat6 for anything in a wall, because the labor is identical and the cable is the cheap part. The room-by-room version of this is on our smart home pre-wire checklist.
Do I have to use the same company for the equipment after the pre-wire?
No. We design the pre-wire to be universal — Cat6A, conduit, back-cans, a structured-wiring panel and room-by-room termination — so any competent integrator can pick it up at trim-out. Roughly speaking, some of our builder projects roll forward into our own installation and some do not, and the labor rate is the same either way. A pre-wire designed to lock a homeowner into one integrator is a pre-wire designed badly.
What is the difference between the pre-wire budget and the finished system budget?
The pre-wire is infrastructure; the finished system is equipment and programming on top of it. A finished home network — gateway, access points, PoE switching, the rack and its UPS — is its own scope, and lighting, audio, theater, shades and security each carry their own. The useful way to hold it in your head: the pre-wire decides what the house is capable of, and the equipment decides what it does on the day you move in. The first one is very hard to change later; the second one is not. Both get quoted fixed, in writing, off the same drawing set.
Who is the structured wiring contractor for new construction in Kansas City?
IntegrateIT (Overland Park, KS — 15108 Glenwood Ave) is a low-voltage trade partner for custom builders across Kansas City, Missouri and the Johnson County suburbs, running alarm, cameras, structured wiring, AV pre-wire, Cat6A, fiber and the Lutron lighting feed under one trade contract — one PO, one certificate of insurance, one punch-list signature. Founded in 2021 by Daniel and Moran Alon. Control4 Platinum Dealer, Crestron Elite Partner, Lutron Certified Dealer, CEDIA member and HTA Certified. Hundreds of homes integrated across the Kansas City metro since 2021. Every install carries a five-year workmanship warranty, the equipment carries its manufacturer warranty, and you have our support for as long as you own the system. Daniel walks every project. Phone: (913) 804-7575 or office@integrateit.tech.
Further reading
Where to go next if this article gave you the framework but you want the brand- or install-specific depth.
Service: new-construction low-voltage · Kansas City
The builder-side version — one trade contract for alarm, cameras, structured wiring, AV pre-wire and the lighting feed.
Read it
The smart home pre-wire checklist
Room by room: how many Cat6A drops, where the access points go, and what to sleeve for later.
Read it
What is a structured wiring system?
The plain-language version of what all this cable is and why it terminates in one place.
Read it
Service: structured wiring rack builds
Where every run lands — sizing, ventilation, UPS and sequencing, labeling, and the as-built.
Read it
What drives the cost of a home network · Kansas City
The equipment side of the same house, by size and platform tier.
Read it
For builders: trade-partner packet
Scheduling, insurance, the ready-for-low-voltage checklist, and how we run a trade on a custom build.
Read it
Priced from the plans, not per square foot.
Send the drawing set. We will mark it up and quote the pre-wire fixed.
Building for a client rather than for yourself? The builder trade-partner packet
Written by Daniel Alon, founder of IntegrateIT LLC — Control4 Platinum Dealer, Crestron Elite Partner, Lutron Certified Dealer, CEDIA member, HTA Certified. Overland Park, KS. Updated 2026-09-01.